Licensing timeline check

Answer a few questions about your satellite to see which US filings and reviews are likely, who handles each one, and how long the regulator says it takes. Every item links to the official page.

Not legal advice. This is a starting checklist built from public regulator pages, not a determination of what you need. Rules change and every mission is different; confirm with each regulator and qualified counsel. Lead times are only shown where an official source publishes one; otherwise we say “Varies; check with the regulator.”

Without JavaScript, every item is shown; check its “Applies when” line.

FCC Part 25 streamlined small-satellite license

FCC Space Bureau · 47 CFR 25.122

Applies when: US operator, commercial service, transmitter on board, ≤10 satellites, ≤180 kg each (incl. propellant), ≥10 cm, non-GSO, deployed at or below 600 km or with propulsion, lifetime ≤6 years.

Lead time: The FCC says a straightforward, uncontested application for a small satellite “may have processing times on the order of 6-9 months”; NGSO applications are placed on public notice within a 60-day timeline, followed by a 30-day comment period. The small-satellite process has “generally shorter processing times” than standard Part 25 (no figure given). Source: FCC: Part 25 licensing process and timeline (updated 23 Jan 2024); FCC: small satellite licensing process

FCC Part 25 space station license (standard)

FCC Space Bureau · 47 CFR Part 25

Applies when: US operator, commercial service, transmitter on board, and the streamlined small-satellite criteria are not met.

Lead time: The FCC says a straightforward, uncontested application “may have processing times on the order of 6-9 months; some applications may take longer”, for example with waivers, bands shared with federal users, novel operations or processing rounds. Source: FCC: Part 25 licensing process and timeline (updated 23 Jan 2024)

FCC Part 5 experimental license (or STA)

FCC Office of Engineering and Technology · 47 CFR Part 5

Applies when: US operator, experiment / demo / research mission, transmitter on board. Experiments of 6 months or less file a Special Temporary Authority; longer ones use Form 442.

Lead time: The FCC's Part 5 FAQ: “Applicants should file three to six months before a launch integration date, but no earlier than a year.” OET also recommends filing no later than 30 days after launch-vehicle determination and in no event later than 90 days before integration; six months before integration is strongly encouraged. Source: FCC: Part 5 experimental FAQ; FCC: how to prepare a USA ITU filing

FCC U.S. market access (only if you'll talk to US earth stations)

FCC Space Bureau · 47 CFR Part 25

Applies when: Non-US operator with a transmitter that will communicate with earth stations in the US or serve the US. Your own national license comes first.

Lead time: The FCC says market-access applicants “will be subject to the same procedures as applicants for U.S. licenses”, so the Part 25 timing above applies. Source: FCC: Part 25 licensing process and timeline

ITU frequency filing (API / notification)

ITU Radiocommunication Bureau, via your administration (FCC for US operators) · ITU Radio Regulations Art. 9 and 11

Applies when: Any satellite with a transmitter. US operators file through the FCC with their application; non-US operators file through their national administration.

Lead time: Under RR No. 9.1, advance publication information goes to the ITU “not earlier than seven years and preferably not later than two years before the planned date of bringing into use”. The ITU's small-satellite guidance puts the process for networks not subject to coordination at “≈ 9 months to 7 years” in total. For Part 5 experiments, the FCC sends the ITU filing only after OET grants the license. Source: ITU: regulatory procedures for small satellites; FCC: how to prepare a USA ITU filing

NOAA commercial remote sensing license

NOAA Commercial Remote Sensing Regulatory Affairs (Office of Space Commerce) · 15 CFR Part 960

Applies when: US operator (or anyone subject to US jurisdiction) with a sensor that images or senses the Earth. Start with CRSRA's initial contact; NOAA can tell you whether a license is needed.

Lead time: By rule, NOAA decides within 7 days whether a submission is complete (15 CFR 960.5(c)) and grants or denies within 60 days of that notice (15 CFR 960.7(b)); if it hasn't acted by then you can request a grant, which comes within 3 days unless NOAA denies or both agree to extend (960.7(c)). No application fee. Source: 15 CFR 960.5; 15 CFR 960.7; NOAA CRSRA FAQ

FAA payload review (through your launch provider)

FAA Office of Commercial Space Transportation · 14 CFR 450.43

Applies when: Your satellite flies on an FAA-licensed launch (US commercial launches). The launch operator normally requests it; a payload owner or operator may also apply. The FAA checks that you hold all required licenses (FCC, NOAA).

Lead time: Varies; check with the regulator.

Export controls: EAR or ITAR

Commerce BIS (EAR) · State DDTC (ITAR) · 15 CFR Parts 730-774 · 22 CFR Parts 120-130

Applies when: US operator. Classify the spacecraft and its parts (most commercial spacecraft are under the EAR, e.g. ECCN 9A515; some items stay on the USML, Category XV). A license may be needed to ship to a foreign launch site or integrator, or to share technical data with foreign persons.

Lead time: BIS: license applications are resolved or referred to the President “no later than 90 calendar days” from registration (15 CFR 750.4(a)(1)); some steps, such as BIS waiting on information from you, don't count. DDTC (ITAR): varies; check with the regulator. Source: 15 CFR 750.4 (BIS)

US export rules on US-origin parts

Commerce BIS (EAR) · State DDTC (ITAR) · 15 CFR Parts 730-774 · 22 CFR Parts 120-130

Applies when: Non-US operator whose spacecraft has US-origin parts or technology, or that ships hardware through the US for launch. US re-export rules can follow those items; your launch provider or integrator will ask.

Lead time: Varies; check with the regulator.

Orbital debris plan and the 5-year disposal rule

FCC (part of your FCC application) · 47 CFR 25.114(d)(14), 5.64(b)(7)

Applies when: Any FCC-authorized satellite (including market access). Below 2,000 km, disposal by atmospheric re-entry must happen “as soon as practicable, but no later than five years following completion of the mission” (FCC 22-74, in force for satellites launched from 29 Sep 2024).

Lead time: No separate filing; it's part of the license application. The FCC recommends allowing extra time to learn NASA's Debris Assessment Software if you haven't used it. Source: FCC: Part 25 licensing process and timeline

Your national space and radio regulator

Your national administration · National law

Applies when: Non-US operator. Most countries require a space-activity authorization, a radio license and the ITU filing through them; some also license Earth imaging.

Lead time: Varies; check with the regulator.

Order of work

  1. Classify the hardware for export control and talk to your launch provider early: they set the integration date the FCC timing is measured from.
  2. Prepare the FCC application with its orbital debris plan (see the deorbit rule check) and ITU filing; for imaging, contact NOAA CRSRA in parallel.
  3. Your launch provider bundles your licenses into the FAA payload review before launch.

Sources checked 19 Oct 2026. Built 19 Oct 2026, 18:59 PT.